| Radioactive Soil Vacuuming for the Rocky Flats Environmental Technology Site.
Phase II
During
September and October 2002, Concept Engineering Group Inc. performed
a Phase II Soil Vacuum Demonstration for the Rocky Flats Environmental
Technology Site. This site is a government-owned former nuclear
weapons plant operated by Kaiser-Hill, LLC for the Department of
Energy. The site is located about 15 miles northwest of Denver,
Colorado. The site's mission today is to safely clean up and close
down Rocky Flats after nearly 40 years of nuclear weapons production.
The objective of the demonstration was to evaluate the capability
of AIR-SPADE’s vacuum excavation technology and equipment to precisely
cut and remove only the fine-grained portion of surface soil representative
of the 903 Lip Area. The 903 Lip Area, an area of approximately
30 acres exceeding Tier II soil action levels, was created when
contaminants from deteriorated drums in the 903 Storage Area were
dispersed by the wind over soils to the east. The 903 Drum Storage
Area was formerly used to store drums containing waste oils and
solvents contaminated with plutonium and uranium. In the 903 Lip
Area, Plutonium-239/240 activities in surface soils range from 6
to 940 pico-curries per gram. As the contamination is thought to
be primarily attached to the fine-grained portion of the first two inches of the soil, the
selective vacuuming capability offers a key benefit for remediation
of the 903 Lip Area by greatly reducing the amount of material for
disposal.
The demonstration was conducted on a 1/2 acre site
at the Church Ranch adjacent to the site Visitor Center on Highway
93. The equipment used in the demonstration is a trailer mounted
SAFEX® 60 unit and a specially configured collector to discharge
via a rotary valve directly into a Lift Liner™ soft-sided
waste container. The unique “flow-thru” design of the
system eliminates a secondary source of dust emissions that would
occur when the tank of a typical vacuum would be emptied when full
into the disposal container. The equipment and method of soil vacuum
remediation is patent pending under US Patent Application 10/680760.
The demonstration successfully met the requirements
in the initial Work Plan. On average soil 1 1/2 inches deep was
excavated per pass of the vacuum equipment at a coverage rate of
350 square feet per hour and an excavation rate of 0.26 bulk cubic
feet per minute. Production efficiency reached 80% at the end of
the demonstration with 100% of the excavated material being retained
in Lift Liner™ soft-sided waste containers.
SAFEX® 60 Skid
Specifications
| Engine type |
35 hp, air cooled, gasoline |
| Fuel tank |
5 US gal |
| Air Compressor |
Rotary screw, 70 scfm, 135 psig, and ASME tank w/ relief |
| Vacuum |
Rotary lobe, 330 scfm, 8 in Hg, industrial silencer |
| Instrumentation |
Air pressure, vacuum, filter pressure drop, tachometer, hour
meter, compressed air temperature, high temperature shut down |
| Controls |
Key ignition switch, engine throttle, and air pressure regulator |
Soil Vacuum System Collector
| Head |
Combined AIR-SPADE air jet / selective vacuum tool |
| Hose |
3 inch diameter smooth bore up to 100 feet long |
| Collector |
Continuous discharge with hydraulic rotary valve |
| Air Filter |
One Tetratex® cartridge |
| Cleaning |
Roto-Pulse™ system on differential pressure |
| Discharge |
Directly into 242 cu ft Lift Liner™ transport bag |
Phase III
In 2003 Phase III of the RFETS Soil Vacuum Demonstration was conducted in the actual 903 Lip area. As shown below, a larger separator was constructed containing an increased filter area. This eliminated an elevated pressure drop noticed during Phase II testing. Because the soil at the actual site was contaminated, a HEPA final filter was added to the equipment skid. A new combined AIR-SPADE® excavation tool / suction head assembly was fabricated. Over a several week time frame, RFETS personnel conducted the testing. Several items were found to be different than in Phase II and than originally thought. The degree of vegetation cover was much higher than the previous year requiring mechanical farm machinery to cut it. The contamination was found also to extend about 6 inches, about 3 times as deep, into the soil.
The 903 clean-up was completed in 2004 using conventional excavation methods. According to RFETS engineering, these methods were effective, but probably removed more dirt than necessary. An EM-50 test summary report is still to be issued, but has been set back due to higher priorities associated with the site closure.
|
|
Special collector filling Lift-LinerTM |
|
|
|
Combined air-jet vacuum head |
|
|
|
| |
SAFEX® Utility with special HEPA filter |
|